Template of Process Measurement Sheet for Organization involved in Design & Construction of Civil Projects
Sr. No
|
Process
Title
|
Process
owner
|
Criteria to
measure the effectiveness of process
|
Target
Effectiveness
|
Actual
Effectiveness
|
Process
Improvement Initiatives
|
1
|
Designing capital projects
|
In charge Civil Design
|
Timely design of facility
|
Within 90% of approved plan.
|
||
2
|
Designing
capital projects
|
In charge
Civil Design
|
Changes in
SCOW after approval
|
Nil
|
1. In light
of head of organization's directives, SCOW Form shall be amended to
incorporate requesting Team's signatures and shall be strictly implemented
between requesting and controlling Teams.
|
|
3
|
Designing
capital projects
|
In charge
Civil Design
|
Detection
of unexpected underground services at
the time of construction
|
Nil
|
To include
site investigation in consultancy/LVC in order to ensure that the selected
locations are free of major underground services.
|
|
4
|
Construction
for Capital projects
|
In charge Construction
|
Changes in
contract
|
50% reduction
in AOs from last year.
|
1. A checklist
to be implemented before commencement of work as per instruction of Team
Incharge.
2. Improvement
in handling of WOs: i) New WO shall follow Team incharge guidelines for new
projects. ii).Verification of WO quantities with actual site work.
|
|
5
|
Construction
for Capital projects
|
In charge Construction
|
Timely
completion of Snag List items.
|
2 months
|
Inspection by
a task team before handing over.
|